Miles Avenue Water Improvement Project

The Indio Water Authority has a construction project underway along Miles Avenue, from Monticello Avenue to Sedona Drive.  The work will entail the installation of 3,700 linear feet of 18-inch diameter pipeline.  The purpose of the project is to increase water pressure and provide additional fire flow capacity in the west part of the City’s water service area. 

PROJECT SUMMARY: 

Project Location:  Miles Avenue from Monticello Avenue to Sedona Drive

Project Schedule:  Construction began on January 24, 2022 and the water main installation has been completed.

What to Expect: Vehicular and pedestrian access will be maintained throughout the project with only minor restrictions for safety. Temporary water outages may be necessary during this work. If your property must undergo a planned temporary water outage, you will receive a separate notice, usually by door hanger, at least 48 hours in advance of the outage. 

Project Contact: Questions or comments can be directed to Indio Water Authority, Roman Gonzalez, Associate Water Engineer, via email at rcgonzalez@indio.org, call office (760) 625-1822 or via cell at (442) 300-8337. 

Please check this webpage regularly as this page is intended to provide the latest project information as the project progresses.

Useful Information:

UPDATES:
Project Status Update as of April 6, 2022 
  • The Miles Ave pipeline has been installed. There will be no further traffic impacts related to this project.
Project Schedule for week of March 4, 2022 (may be subject to change):
  • TRAFFIC ALERT:  Striping work will be taking place this week. The traffic signal will be on red flash at the intersection of Miles Ave and Jefferson from Monday - Tuesday, April 4-5, from 9:00am - 3:00pm.  Traffic is expected to get backed up. Avoid this area if possible.
Project Schedule for week of March 28, 2022 (may be subject to change):
  • TRAFFIC ALERT:  Work continues along Miles Ave.  Traffic is expected to get backed up at the Miles Ave and Jefferson intersection while the signal is on red flash from Tuesday through Thursday, March 29-31st from 8:30am - 6:00pm.  Avoid this area if possible.
Project Schedule for week of March 21, 2022 (may be subject to change):
  • TRAFFIC ALERT:  Paving is scheduled to occur at the project site on Friday, March 25th.  Traffic is expected to get backed up at Miles Ave and Jefferson while the signal is on red flash from 8:30am - 6:00pm.  Avoid this area if possible.
Project Schedule for week of March 14, 2022 (may be subject to change):
  • Work for "tie in" on the East side of Miles Ave. and Sedona Drive. Work will also be focused on paving of street.
Project Schedule for week of March 7, 2022 (may be subject to change):
  • Night work is scheduled to occur at the intersection of Miles Ave. and Jefferson St. 
Project Schedule for week of February 28, 2022 (may be subject to change):
  • Work continues with the "tie in" of the newly added water mainline to the existing water main infrastructure.  Work will occur on the east side of Miles Ave. 
Project Schedule for week of February 21, 2022 (may be subject to change):
  • Day work is scheduled to occur at the intersection of Miles Avenue and Jefferson St. Night work is scheduled to occur at the intersection on February 24th.
Project Schedule for week of February 14, 2022 (may be subject to change):
  • Work will continue primarily along Miles Ave. This includes work related to "tie in" to existing water mainline.
Project Schedule for week of February 7, 2022 (may be subject to change):
  • Water mainline installation on Miles Ave. east of Jefferson St.
  • Night work will continue on the intersection of Jefferson St. and Miles Ave. from 7:00 P.M. to 3:00 A.M.
Project Schedule for week of January 31, 2022 (may be subject to change):
  • 01/31/2022: Pothole work will occur on Miles Avenue, east of Jefferson St.
  • 02/01/2022 thru 02/02/2022:  Night work will occur on the intersection of Jefferson St. and Miles Ave from 7:00 P.M. to 3:00 A.M.  Properties located near the intersection were provided a separate notice regarding overnight work. A copy of the notice can be found here
  • 02/03/2022 thru 02/04/2022: Water mainline installation on Miles Ave. west of Jefferson St.
 

 